📧 sales@tanksco.com | 📞 918-791-1456 | American Made Quality

Pre-Installation Requirements

Essential preparations before tank delivery

📐

Site Preparation

Level, compacted surface capable of supporting full tank weight. Concrete pad recommended for tanks over 50,000 gallons. Ensure proper drainage and consider future maintenance access.

🚚

Access Requirements

Clear path for delivery truck and crane access. Minimum 20 feet overhead clearance for vertical placement. Road width minimum 20 feet with adequate turning radius.

Utilities & Services

Electrical connections for pumps and controls. Water source for testing and commissioning. Proper drainage for overflow and maintenance. Consider future instrumentation needs.

Installation Steps

Follow these steps for proper tank installation

1
Foundation Preparation

Foundation Requirements:

  • Level surface with maximum 1/8" per foot slope
  • Compacted gravel base minimum 6" thick or reinforced concrete pad
  • Pad diameter = tank diameter + 2 feet minimum on all sides
  • Consider drainage slope away from foundation (minimum 2% grade)
  • Install moisture barrier under concrete pads
  • Allow concrete to cure minimum 7 days before tank placement
💡

Pro Tip

For tanks over 75,000 gallons, we recommend a reinforced concrete pad with #4 rebar on 12" centers and anchor bolt provisions for seismic restraint. Consult local building codes for specific requirements.

Foundation Specifications by Tank Size:

  • 15,000-30,000 gallons: 6" compacted gravel or 4" concrete
  • 30,000-75,000 gallons: 6" reinforced concrete recommended
  • 75,000+ gallons: 8-12" reinforced concrete required
2
Tank Delivery & Unloading

Pre-Delivery Checklist:

  • Verify site access routes are clear and adequate
  • Confirm crane positioning and capacity
  • Check weather conditions - avoid high winds
  • Have installation crew ready on-site

Unloading Procedure:

  • Inspect tank for shipping damage before unloading - document any issues
  • Use appropriate lifting equipment (crane capacity = 2x tank empty weight minimum)
  • Attach lifting straps ONLY to designated lifting lugs
  • Use spreader bars to prevent tank deformation
  • Never lift tank by fittings, manways, or sidewalls
  • Control tank movement with tag lines during lifting
⚠️

Safety Warning

Always use certified rigging equipment rated for minimum 2x tank weight. Keep all personnel outside the fall zone during lifting operations. Never work under suspended loads.

3
Tank Positioning

Positioning Guidelines:

  • Center tank on prepared foundation using centerline marks
  • Ensure tank is perfectly vertical using 4-foot level on multiple sides
  • Maximum out-of-plumb: 1/4" per 10 feet of height
  • Orient inlet/outlet fittings for optimal piping layout
  • Maintain minimum clearances from buildings and property lines
  • Allow 360° access for maintenance operations

Minimum Clearance Requirements

Concrete Foundation TANK Building Property Line Min. 5 ft Min. 10 ft Min. 2 ft Min. 2 ft Minimum Clearances: • Building: 5 ft • Property Line: 10 ft • Adjacent Tanks: 3 ft • Foundation: +2 ft all sides
4
Anchoring & Securing

Anchoring Methods:

  • Install anchor bolts per manufacturer specifications
  • Use stainless steel or galvanized hardware for corrosion resistance
  • Torque bolts to specified values (typically 50-75 ft-lbs)
  • Install seismic restraints as required by local codes
  • Add wind load cables for exposed locations (winds >100 mph)
  • Document all anchor points with photos for warranty

Seismic Requirements:

  • Zone 1-2: Standard anchoring typically sufficient
  • Zone 3: Additional restraints required
  • Zone 4: Full seismic restraint system mandatory
💡

Code Compliance

Always check local building codes for specific anchoring requirements. California, for example, requires CBC-compliant seismic restraints for all tanks over 5,000 gallons.

5
Piping Connections

Connection Guidelines:

  • Use flexible connections to prevent stress on tank fittings
  • Support all piping independently with proper hangers
  • Install proper gaskets and use appropriate sealants (NSF approved for potable water)
  • Add isolation valves within 3 feet of tank connections
  • Install unions for easy maintenance access
  • Slope all piping for proper drainage

Required Connections:

  • Inlet piping: Anti-siphon valve and air gap required
  • Outlet: Emergency shutoff valve accessible from ground level
  • Overflow: Pipe to safe discharge area, minimum 1.5x inlet size
  • Drain: Full-port valve for complete tank drainage
  • Vent: Atmospheric vent with insect screen
  • Level indicator: Connection for gauge or sensor
⚠️

Critical Safety

Never create a closed system. Always ensure proper venting to prevent vacuum collapse or pressure buildup. Install vacuum/pressure relief valves on all sealed tanks.

6
Testing & Commissioning

Testing Procedure:

  • Perform visual inspection of all connections and fittings
  • Check torque on all bolted connections
  • Conduct hydrostatic test - fill tank slowly (max 2 ft/hour)
  • Fill to 6 inches, stop and check for leaks
  • Continue filling in stages, checking at 25%, 50%, 75%, and 100%
  • Hold at full capacity for minimum 24 hours
  • Check for leaks at all fittings, seams, and connections
  • Verify proper operation of all valves and vents
  • Test overflow system functionality
  • Document test results with photos and sign-off sheet
⚠️

Important Testing Notes

Never exceed design pressure during testing. Fill tank slowly to prevent hydraulic shock. For chemical storage tanks, always test with water first before introducing chemicals.

Final Commissioning:

  • Drain test water if switching to different contents
  • Clean and sanitize for potable water applications
  • Install and calibrate level monitoring systems
  • Label all valves and controls
  • Provide operation manual to facility personnel
  • Schedule initial maintenance inspection

Installation Checklist

Foundation properly prepared and level
Tank inspected for shipping damage
Proper lifting equipment and rigging used
Tank positioned and leveled correctly
Anchoring system installed per specs
All piping connections completed
Overflow and vent systems installed
Valves and controls operational
Hydrostatic test completed successfully
Level monitoring system installed
Documentation and photos completed
Site cleaned and secured

Common Installation Issues

Avoid these common mistakes

⚠️ Uneven Foundation

Can cause tank stress, premature failure, and warranty void. Always verify level with precision equipment before final positioning. Maximum tolerance is 1/8" per foot.

⚠️ Improper Lifting

Lifting from wrong points can cause permanent tank damage. Only use designated lifting lugs and proper spreader bars. Never attach rigging to fittings or tank walls.

⚠️ Rigid Piping

Can cause fitting failure due to thermal expansion and tank movement. Always use flexible connections and support piping independently from tank.

⚠️ Inadequate Venting

Can cause tank collapse or rupture. Ensure proper atmospheric venting and never create a sealed system. Size vents per API standards.

⚠️ Missing Overflow

Risk of tank damage and environmental issues. Overflow must be 1.5x inlet size minimum and discharge to safe area away from foundations.

⚠️ Poor Drainage

Standing water can undermine foundation and cause corrosion. Ensure minimum 2% slope away from tank and install French drains if necessary.